Background: Solo owner-operator with a small crew, typically running 2–4 concurrent projects in the $150K–$300K range, billing on a traditional draw schedule tied to project phases. When cash is tight — the mechanics: On a $280,000 kitchen-and-addition project, standard practice was to order materials and pay subcontractor deposits as soon as a phase began — but the client draw for that phase wasn't due until the phase was complete. That structural mismatch meant $35,000–$50,000 was consistently out of pocket for roughly 3 weeks per phase. Action taken:
Result: The out-of-pocket gap per draw shrank from roughly 3 weeks to under 5 days, effectively eliminating the need to self-finance materials on future projects. Underlying principle: If your billing triggers don't match your cost triggers, you are financing your clients' projects with your own capital, often without realizing it. Fix the timing mismatch before you fix anything else. When flush with cash — the mechanics: Three large projects closed within the same month — a scheduling coincidence rather than a plan — leaving about $110,000 in surplus, right when a $60,000 skid steer purchase was also on the table.
Action taken:
Result: Capacity expanded for the next bid season without touching the safety net — a decision that would have looked "conservative" in the moment but paid off six months later when a slower quarter hit. Underlying principle: A surplus tied to project timing (not steady demand) is exactly the kind of cash that feels permanent but isn't. Reserve first, then grow — never the other way around, even when the growth spending looks obviously worth it.
0 Comments
Leave a Reply. |
Categories
All
|